Any plant/organizational change must be 
identified, assessed and authorized by the 
responsible of the work place.


Management System of Change


PLAN

• Identify, analyze and assess any change or deviation to plant 
design, work procedures/practices and organization.
• Support any change, in particular overriding/disabling/change 
of a safety critical element, with a specific risk assessment.

READY?

• Is the change, in particular deviations from mandatory 
requirements, duly structured, documented and approved by 
a Company authorized and competent person?
• Is the change properly recorded and tracked in a dedicated 
system?

Safety Management System



GO!

• Communicate any change to all concerned personnel and keep 
track of the identified and implemented actions