Lifting operations properly planned,
implemented and monitored, prevent
the workers risk of falling or being
crushed or struck.
PLAN
• Plan the lift with a specific risk assessment.
• Always inspect the equipment/machines and accessories as
per
manufacturer’s instructions and site procedure requirement:
check and record damages, color code, SWL and certificate.
• Lifting authority be involved in all activities.
• Personnel lifts shall be done only with man-rated equipment
and under a PTW.
READY?
• Is lifting equipment certified by a Third Party in accordance
with
relevant local legislation or international standards and
regularly
maintained according to the planned schedule?
• Are all persons engaged in lifting and hoisting operations
competent for that role and supervised at all times?
• Are lifting and hoisting equipment, machines and
accessories
(cranes, forklifts, slings, handles, hooks, baskets, etc.) in
good
condition according to national legislation and international
best practices?
• Have you verified that the lifting area is marked out
to prohibit unauthorized access?
• Are the PPEs identified by the Employer in the specific
risk
assessment for the required task, in good condition and worn
by all people?
GO!
• Always ensure the presence of a banksman during the entire
lifting operation and avoid unplanned blind lifts.
• Never allow personnel to be under or close to suspended
loads for any reason.
• Ensure that the lifting operator keeps the
machine/equipment
under control at all time.